CIPS L6M5 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Strategic Programme Management | - Programme governance and alignment with organisational strategy - Defining programme scope and objectives |
| Stakeholder and Change Management | - Managing organisational change in programmes - Stakeholder engagement strategies |
| Risk, Performance and Benefits Management | - Measuring programme performance and benefits realisation - Programme risk identification and mitigation |
| Leadership in Programme Delivery | - Team coordination and cross-functional collaboration - Leadership styles and influencing stakeholders |
Inside Our CIPS Strategic Programme Leadership Practice Material
None that matter: downloads are unlimited and there is no meter on usage time, so you can reinstall the engine and practice with the L6M5 questions as often as you need. The software runs on Windows with a standard Java environment and simulates the real exam scenario session after session.
This package includes 85 practice questions for the CIPS Strategic Programme Leadership exam. Every answer is verified by an experienced team of experts, so you can trust what you study.
You can register for the CIPS Strategic Programme Leadership exam through the official channels:
Completion of CIPS Level 5 Advanced Diploma or equivalent experience recommended
You can confirm the current eligibility requirements on the official L6M5 exam page before you register.
Many candidates combine practice questions with official training. Recommended options include:
Yes. The PDF version works well as training and teaching material: print it for classroom sessions, share it across a certification study group, or use it as handout content during internal courses. Many company buyers choose this version for exactly that purpose, and printing is unlimited.
The CIPS Strategic Programme Leadership practice questions are organized around the official exam objectives. Key topics include:
- Leadership in Programme Delivery ()
- Strategic Programme Management ()
- Stakeholder and Change Management ()
Team training sessions can follow this topic list to keep everyone on the same page.
CIPS Strategic Programme Leadership Sample Questions:
Skipped
Under what circumstances can Specific Performance be used to compensate an innocent party for a contractual breach? Select all that apply.
- A. When the innocent party wishes to avoid going to court
- B. Money cannot remedy the situation, such as in the case of the sale of rare goods
- C. A contract has a liquidated damages clause
- D. The innocent party did not fulfil their contractual obligations under the contract
- E. Adequate remedies are not available
Correct Answer: B,E 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
"Persuasion should be a last resort in cultural change." Is this statement true?
Answer Options:
- A. No - persuasion should be planned before implementing change
- B. No - persuasion is not useful in large cultural shifts
- C. Yes - persuasion should only be used after coercion has failed
- D. Yes - persuasion should be linked to an implicit or perceived threat
Correct Answer: A 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Sarah is a Project Manager running a project to create a new type of shoe that is sensitive due to intellectual property issues. She is undergoing Programme Level Control. What is the purpose of Programme Level Control?
- A. to provide additional resources to ensure the project is completed on time
- B. to ensure the project is running to the allocated budget
- C. to ensure the project remains a secret
- D. to track how much money the project has spent
Correct Answer: A 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
What is the purpose of the Project Team at Glitter Kitten Ltd?
Answer Options:
- A. Contract Negotiation
- B. Critical Path Analysis
- C. Supply Chain Mapping
- D. Value Engineering
Correct Answer: D 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).
Jerry is responsible for starting a new construction project.
His company wants to build a new Water Park on the outskirts of town.
He has prepared a Statement of Need, outlining requirements and benefits.
Senior Management has approved the project to move forward.
Q: What should be Jerry's next task?
Answer Options:
- A. Appointment of a construction manager to manage the project
- B. Project brief - creating a list of technical requirements
- C. Concept design - outlining how the water park would look and operate
- D. Feasibility study - looking in-depth at options available
Correct Answer: D 🗳️
Explanation: Only visible for ExamCost members. You can sign-up / login (it's free).