[Q98-Q123] USGBC LEED-AP-BD-C Practice Verified Answers - Pass Your Exams For Sure! [2024]

Share

USGBC LEED-AP-BD-C Practice Verified Answers - Pass Your Exams For Sure! [2024]

Valid Way To Pass USGBC LEED's LEED-AP-BD-C Exam

NEW QUESTION # 98
The LEED project has a main entrance and two service entrances in an alley behind the building. Which entrances need non-smoking signage and at what maximum distance from the door(s) can the non-smoking signage be posted?

  • A. At the main entrance and the two service entrances, 25 ft. (7.5 m) from the doors
  • B. At the main entrance and the two service entrances, 10 ft. (3 m) from the doors
  • C. At the main entrance, 25 ft. (7.5 m) from the door
  • D. At the main entrance, 10 ft. (3 m) from the door

Answer: B

Explanation:
Explanation
According to the LEED v4 Reference Guide for Building Design and Construction, no smoking signage must be placed within 10 feet (3 meters) of every building entrance, except for alarmed emergency exits. This applies to both the main entrance and the service entrances, regardless of their location or frequency of use.
The signage is intended to communicate the no-smoking policy to occupants and visitors and prevent environmental tobacco smoke from entering the building. References: EQ Prerequisite Environmental Tobacco Smoke Control, LEED v4 Reference Guide for Building Design and Construction123


NEW QUESTION # 99
A project elects to pursue Location and Transportation Credit, Surrounding Density and Diverse Uses, Option
2. Diverse Uses because of the project's location in an amenity-rich area. The project features 18 uses overall, including at least four uses in three of the five use type categories. What threshold must the project surpass in order to demonstrate exemplary performance for Option 2?

  • A. 15 uses, including at least one Food Retail and one Community Anchor use
  • B. 15 uses, including two uses in each of the five categories
  • C. Exemplary Performance is not available for Option 2
  • D. 18 uses, including uses in at least four of the five use type categories

Answer: C

Explanation:
Explanation
Exemplary Performance is not available for Option 2 of Location and Transportation Credit, Surrounding Density and Diverse Uses. According to the LEED v4 BD+C Reference Guide, this credit has two options:
Option 1. Surrounding Density (5 points) and Option 2. Diverse Uses (1 point).Exemplary Performance is only available for Option 1, and it requires achieving a surrounding density of at least 405,000 square feet per acre (100,000 square meters per hectare)1.Option 2 does not have any Exemplary Performance criteria, and it only requires locating the project within a 1/2-mile (800-meter) walking distance of at least seven diverse uses2.
References:
* Credit: Surrounding density and diverse uses | U.S. Green Building Council
* Surrounding Density and Diverse Uses - LEED v4


NEW QUESTION # 100
A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?

  • A. Sustainable Sites Credit, Rainwater Management and Water Efficiency Credit, Indoor Water Use Reduction
  • B. Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Indoor Water Use Reduction
  • C. Sustainable Sites Credit, Rainwater Management and Water Efficiency Prerequisite, Indoor Water Use Reduction
  • D. Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Outdoor Water Use Reduction

Answer: A

Explanation:
Explanation
A rainwater harvesting system on site could be recognized in the Sustainable Sites Credit, Rainwater Management and the Water Efficiency Credit, Indoor Water Use Reduction. The Sustainable Sites Credit, Rainwater Management rewards projects that reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site1. A rainwater harvesting system can help achieve this by capturing and reusing rainwater on site2. The Water Efficiency Credit, Indoor Water Use Reduction rewards projects that reduce indoor water consumption by installing water-efficient fixtures and fittings3. A rainwater harvesting system can help achieve this by providing an alternative source of water for non-potable uses such as toilet flushing and irrigation4.
The other options are not correct. The Water Efficiency Credit, Water Metering does not recognize rainwater harvesting systems, but rather requires projects to install permanent water meters that measure the total potable water use for the building and grounds. The Water Efficiency Prerequisite, Outdoor Water Use Reduction does not recognize rainwater harvesting systems, but rather requires projects to reduce outdoor water consumption by using plant species that are native or adapted to the region and by using irrigation systems that are efficient and properly controlled. The Water Efficiency Prerequisite, Indoor Water Use Reduction does not recognize rainwater harvesting systems, but rather requires projects to reduce indoor water consumption by 20% from the baseline by installing water-efficient fixtures and fittings.
References:
*Rainwater Management, p. 1
*NC-v4 SSc4: Rainwater management, p. 2
*Indoor water use reduction, p. 1
*NC-v4 WEc3: Indoor water use reduction, p. 3
*[Water metering], p. 1
*[Outdoor water use reduction], p. 1
*[Indoor water use reduction], p. 2


NEW QUESTION # 101
To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

  • A. all luminaires have full cutoff fixtures
  • B. all luminaires have a minimum color temperature of 3500 K
  • C. all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone
  • D. all luminaires are mounted at least three mounting heights from the lighting boundary

Answer: C

Explanation:
Explanation
To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate that all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone. The MLO lighting zone is determined by the site-specific characteristics and the definitions provided in the IES/IDA MLO User Guide1. The fixture ratings are based on the backlight-uplight-glare (BUG) system, which measures the amount of light emitted in different directions by a luminaire, as defined in IES TM-15-11, Addendum A2. The maximum allowable ratings for each lighting zone are given in Table 1 of the credit language3. References: IES/IDA MLO User Guide; IES TM-15-11, Addendum A; Light pollution reduction


NEW QUESTION # 102
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

  • A. No action is necessary as the PV system is not required to be commissioned
  • B. The building's mechanical engineer should commission his own installations and share the results with the project owner
  • C. The PV system installer should commission his own installations and share the results with the project owner
  • D. The Cx agent for the project must conduct or oversee the Cx of the PV system

Answer: D

Explanation:
Explanation
The correct answer is C, the Cx agent for the project must conduct or oversee the Cx of the PV system.
According to the LEED v4 Reference Guide for Building Design and Construction, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires that all energy-related systems, including renewable energy systems such as PV, be commissioned by an independent commissioning agent (CxA) or a qualified member of the project team who reports to the owner. The CxA or the qualified team member must perform or oversee all commissioning activities, including developing a commissioning plan, reviewing design documents and submittals, verifying installation and performance, and preparing a commissioning report12 References: 1: LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Fundamental Commissioning and Verification, page 562. 2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1020.


NEW QUESTION # 103
During a design charrette, community neighbors raise a concern about potential glare resulting from a project's highlyreflective roof. Which option should the LEED AP recommend to best address these concerns?

  • A. Install a vegetative roofing system
  • B. Change the design to reduce the amount of roofing area
  • C. Increase the parapet height
  • D. Change the roofing material to a dark material to eliminate the issue

Answer: A

Explanation:
Explanation
Installing a vegetative roofing system is the best option to address the potential glare resulting from a project's highly reflective roof. A vegetative roofing system, also known as a green roof, is a roof that is partially or completely covered with vegetation and a growing medium, planted over a waterproofing membrane. A vegetative roofing system can reduce the reflectivity of the roof surface and mitigate the glare impact on the surrounding environment. It can also provide other benefits, such as reducing heat island effects, improving stormwater management, enhancing biodiversity, and increasing roof insulation. Therefore, option A is the correct answer. The other options are not as effective or desirable as installing a vegetative roofing system.
Changing the design to reduce the amount of roofing area (option B) may not be feasible or desirable, as it may compromise the project's program or performance. Changing the roofing material to a dark material to eliminate the issue (option C) may reduce the glare, but it will also increasethe heat absorption and emission of the roof, contributing to heat island effects and increasing cooling loads. Increasing the parapet height (option D) may block some of the glare, but it will also increase the material and construction costs, and it may not be sufficient to prevent glare from all angles.For more information on vegetative roofing systems and their benefits, you can refer to the LEED v4 Reference Guide for Building Design and Construction1or the Green Roofs for Healthy Cities website2.


NEW QUESTION # 104
Which of the following is a leadership extraction practice that rewards projects for choosing materials with closed-loop recycling and take-back programs in LEED?

  • A. Extended producer responsibility
  • B. Material reuse
  • C. Bio-based elements
  • D. Forest Stewardship Council (FSC) wood products

Answer: A

Explanation:
Explanation
Extended producer responsibility
Extended producer responsibility is a leadership extraction practice that encourages manufacturers to take back their products or packaging at the end of their useful life and recycle them in a closed-loop system. This reduces the environmental impacts of extraction, transportation, and disposal of raw materials. LEED rewards projects for choosing materials that have extended producer responsibility programs or policies in place.
References:
* Reference Guide for Building Design and Construction v4 - Pages 263-2641
* LEED v4: Building Design + Construction Guide - U.S.Green Building Council2


NEW QUESTION # 105
Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

  • A. Healthcare
  • B. Core and Shell
  • C. Schools
  • D. Retail

Answer: A


NEW QUESTION # 106
The use of lead, mercury, copper and cadmium should be limited because they all

  • A. take an unreasonable amount of energy to recycle
  • B. interfere with the magnetic instruments in a medical building
  • C. are persistent bioaccumulative toxins
  • D. reduce the life cycle assessment of a building

Answer: C

Explanation:
Explanation
According to the LEED v4: Building Design + Construction Guide, lead, mercury, copper and cadmium are examples of persistent bioaccumulative toxins (PBTs) that should be limited in building products. PBTs are substances that remain in the environment for long periods of time, accumulate in living organisms, and pose health risks to humans and wildlife. One of the prerequisites for the Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients, is to reduce the use of products that contain PBTs above certain thresholds1. References: LEED v4: Building Design + Construction Guide, Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients, Option 3: Product Manufacturer Supply Chain Optimization1


NEW QUESTION # 107
Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite,Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

  • A. 140,000 ft2 (13 006 m2) retail project
  • B. 110,000 ft2 (10 219 m2) school project
  • C. 80,000 ft2 (7 432 m2) hospital project
  • D. 50,000 ft2 (4 645 m2) office project

Answer: B

Explanation:
Explanation
The Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance:
ASHRAE 50% Advanced Energy Design Guide allows projects to follow the recommendations of the ASHRAE 50% Advanced Energy Design Guides (AEDGs) for different building types and climate zones. The AEDGs provide design guidance for buildings that use 50% less energy than those built to the requirements of the ANSI/ASHRAE/IES Standard 90.1-2004 commercial code1. However, not all building types and sizes are covered by the AEDGs. According to the LEED Reference Guide for Building Design and Construction2, the following building types and sizes are eligible for this option:
* Small to Medium Office buildings up to 100,000 ft2 (9 290 m2)
* Medium to Large Retail buildings up to 100,000 ft2 (9 290 m2)
* K-12 School buildings up to 200,000 ft2 (18 580 m2)
* Warehouse and Distribution Center buildings up to 500,000 ft2 (46 450 m2) Therefore, among the given options, only the school project is eligible to pursue this option, as it falls within the size limit for the K-12 School AEDG3.
References:
* LEED Reference Guide for Building Design and Construction v4
* Minimum Energy Performance - ASHRAE 90.1 - 2010
* ASHRAE 50% Advanced Energy Design Guide for K-12 School Buildings
* Advanced Energy Design Guides | Department of Energy


NEW QUESTION # 108
A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of

  • A. 15,000 ft2 (1 400 m2)
  • B. 25,000 ft2 (2 300 m2)
  • C. 35,000 ft2 (3 250 m2)
  • D. 12,500 ft2 (1 160 m2)

Answer: B

Explanation:
Explanation
According to the LEED v4 Reference Guide for Building Design and Construction, Option 1 of the Site Development - Protect or Restore Habitat credit requires restoring 25% of the site area (including the building footprint) with native or adapted vegetation1. To achieve exemplary performance, the project must double the credit requirements and restore 50% of the site area2. In this case, the site area is 100,000 ft2 (9 290 m2), so the project must restore 50,000 ft2 (4 645 m2) with vegetation. The project already has 35,000 ft2 (3 250 m2) of native vegetated open space, so it needs to add another 15,000 ft2 (1 395 m2) of vegetation. Since the on-grade surface is fully occupied by the building footprint and the asphalt parking, the only option is to incorporate a vegetated roof. Therefore, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of 15,000 ft2 (1 395 m2). References: SS Credit Site Development - Protect or Restore Habitat, LEED v4 Reference Guide for Building Design and Construction13


NEW QUESTION # 109
The LEED AP has identified a pilot credit that is relevant to the project. This would be documented in LEED Online as a(n)

  • A. Innovation Credit
  • B. Regional Priority Credit
  • C. Special Circumstances within a related credit
  • D. Exemplary Performance for a related credit

Answer: A

Explanation:
Explanation
A pilot credit identified by the LEED AP that is relevant to the project would be documented in LEED Online as an Innovation Credit.Pilot credits are proposed credits that are used to test and evaluate a strategy before they can be considered for incorporation into the LEED consensus process for approval by USGBC membership1.All other LEED v4 and v4.1 projects may register for pilot credits and pilot ACPs in LEED Online1.
References:Pilot credits and pilot alternative compliance paths (ACPs)


NEW QUESTION # 110
A developer is considering an urban infill site for a new commercial building rather than a rural greenfield site adjacent to a stream. Which of the following is an economic advantage of the infill site?

  • A. Reduces need for new utility infrastructure
  • B. Preserves habitat and natural resources
  • C. Protects greenfields and farmland
  • D. Reduces potential damage to an existing stream

Answer: A

Explanation:
Explanation
An economic advantage of the infill site is that it reduces the need for new utility infrastructure. This is because the infill site is located within an existing urban area that already has access to water, sewer, electricity, and other utilities1. The developer can save on the costs of extending or installing new utility lines and services to the rural greenfield site, which may not have adequate or reliable utility infrastructure2. The other options are not economic advantages, but rather environmental benefits of the infill site. Protecting greenfields and farmland, preserving habitat and natural resources, and reducing potential damage to an existing stream are all positive outcomes of avoiding development on the rural greenfield site, but they do not directly translate into monetary savings for the developer3.
References:
*High-priority site, p. 1
*The Economics of Infill Development, p. 2
*LEED v4 for Building Design and Construction, p. 69


NEW QUESTION # 111
During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractorsubstituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

  • A. Equipment Maintenance Plan
  • B. Coordination of other contractors
  • C. Energy meter location
  • D. Owner's Project Requirements

Answer: D

Explanation:
Explanation
The Owner's Project Requirements (OPR) is a document that defines the goals, expectations, and performance criteria of the project, as established by the owner or the owner's representative1. The OPR is one of the key deliverables of the commissioning process and serves as the basis for the design, construction, and operation of the building systems. Therefore, the priority for the Commissioning Authority (CxA) to consider when the contractor substitutes a higher efficiency piece of equipment is whether the substitution meets or exceeds the OPR. The CxA should verify that the new equipment is compatible with the OPR and does not compromise the performance, functionality, or reliability of the system. The CxA should also communicate the substitution to the owner and the design team and document the change in the commissioning plan and report.
References:
* LEED Reference Guide for Building Design and Construction v4
* The Role of a Commissioning Agent (CxA) - cxplanner.com
* Commissioning Authority | WBDG - Whole Building Design Guide
* General Commissioning Requirements - Northwestern University


NEW QUESTION # 112
Which of the following items must have safe collection, storage, and disposal for Materials andResources Prerequisite, Storage and Collection of Recyclables?

  • A. Medical waste
  • B. Electronic waste
  • C. Landscape waste
  • D. Food waste

Answer: B

Explanation:
Explanation
This option requires the project to provide safe collection, storage, and disposal for electronic waste, such as computers, monitors, printers, and batteries, because it contains hazardous materials that can harm human health and the environment if not handled properly1. Electronic waste can be recycled or reused by certified e-waste recyclers or manufacturers2.
References: = [LEED v4: Building Design + Construction Guide], Recycled content.


NEW QUESTION # 113
In the step-by-step guidance for Location and Transportation Credit, Bicycle Facilities, which of the following requirements can define a bicycle network?

  • A. Traffic lights
  • B. One-way streets
  • C. Bike share
  • D. Slow speed roadways

Answer: D


NEW QUESTION # 114
Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

  • A. A standard garbage disposal
  • B. Electronic submeter at the domestic water supply pipe to the building
  • C. Commercial dishwasher that is ENERGY STAR® labeled or performance equivalent
  • D. An open-loop HVAC system that discharges potable cooling water to a nearby lake

Answer: C

Explanation:
Explanation
The Water Efficiency Credit, Indoor Water Use Reduction aims to reduce indoor water consumption by installing water-efficient fixtures and fittings, such as faucets, showerheads, toilets, and urinals1. A commercial dishwasher that is ENERGY STAR® labeled or performance equivalent would help reduce the water use for dishwashing, which is one of the process water uses included in the credit calculation2. A standard garbage disposal would not reduce water use, but rather increase it. An electronic submeter at the domestic water supply pipe to the building would help measure and monitor water use, but not directly reduce it. An open-loop HVAC system that discharges potable cooling water to a nearby lake would waste a lot of water and potentially harm the environment.
References:
Indoor Water Use Reduction
"Maximizing Water Efficiency in Commercial Buildings: Understanding LEED BD+C Water Efficiency Credits"


NEW QUESTION # 115
A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?

  • A. Install a preferred drop-off lane for buses meeting the emission requirements
  • B. Provide calculations showing that the average fleet bus meets the emission requirements
  • C. Document that all buses serving the project achieve a minimum green score of 30 on the American Council foran Energy Efficient Economy (ACEEE) annual vehicle rating guide
  • D. Inventory the school fleet to develop and create a plan for all buses to meet the emission requirements

Answer: D

Explanation:
Explanation
According to the LEED v4: Building Design + Construction Guide, Option 2 of the Location and Transportation Credit, Green Vehicles requires the project to inventory the school fleetto develop and create a plan for all buses to meet the emission requirements. The plan must include a timeline for implementation and a budget. The emission requirements are based on the U.S. Environmental Protection Agency (EPA) standards for heavy-duty vehicles1. References: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Green Vehicles, Option 2: Green Buses or School-Owned Vehicles1


NEW QUESTION # 116
The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

  • A. Create positive pressure in the room
  • B. Use MERV 8 (F5), or higher, filters
  • C. Provide a large opening to dilute air contaminates
  • D. Provide a hard-lid ceiling

Answer: D

Explanation:
Explanation
The Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies aims to establish better quality indoor air for the building occupants that promotes their comfort and well-being1. This credit requires the project team to implement several strategies to reduce the exposure of occupants and HVAC systems to environmental tobacco smoke, airborne contaminants, and chemicals1. One of the strategies is to design and construct all interior partitions to full height (deck-to-deck) or provide a hard-lid ceiling for spaces where hazardous gases or chemicals may be present or used2. This strategy helps prevent the migration of contaminants from one space to another through the plenum3. A copy room is an example of such a space, as it may contain printers, copiers, toners, and solvents that can emit volatile organic compounds (VOCs) and particulate matter (PM) into the air4. Therefore, the project team can achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies by providing a hard-lid ceiling for the copy room.
References:
* Enhanced Indoor Air Quality Strategies
* Enhanced Indoor Air Quality Strategies - Canada Green Building Council
* [LEED Reference Guide for Building Design and Construction v4], page 631
* Copy Rooms: A Source of Indoor Air Pollution


NEW QUESTION # 117
Which of the following Water Efficiency credits differ between LEED Building Design and Construction:
New Construction and LEED Building Design and Construction: Healthcare?

  • A. LEED Building Design and Construction: New Construction has no Water Efficiency Credit, Cooling Tower Water Use
  • B. LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction
  • C. LEED Building Design and Construction: Healthcare has no Water Efficiency Credit, Cooling Tower Water Use
  • D. LEED Building Design and Construction: New Construction has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction

Answer: B

Explanation:
Explanation
LEED Building Design and Construction: Healthcare has additional appliance and process water requirements in Water Efficiency Prerequisite, Indoor Water Use Reduction LEED Building Design and Construction: New Construction and LEED Building Design and Construction:
Healthcare have the same Water Efficiency credits, except for the Cooling Tower Water Use credit, which is only applicable to the former. However, the Indoor Water Use Reduction prerequisite differs between the two rating systems, as the Healthcare version requires additional calculations for appliance and process water use, such as medical equipment, laundry, and kitchen equipment.
References:
Reference Guide for Building Design and Construction v4 - Pages 256-3171 LEED v4: Building Design + Construction Guide - U.S. Green Building Council2


NEW QUESTION # 118
A comprehensive rainwater management plan may include design elements such as

  • A. soil compaction, swales, vegetated roofs and xeriscaping
  • B. cisterns, porous pavement, swales and vegetated roofs
  • C. bioretention pond, cisterns, porous pavement and stabilized construction entrance
  • D. artificial turf, bioretention pond, cisterns and hay bales

Answer: B

Explanation:
Explanation
These design elements are examples of low-impact development (LID) and green infrastructure (GI) practices that can reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site1. Cisterns can collect and store rainwater for reuse or infiltration, porous pavement can allow water to seep into the ground, swales can convey and filter stormwater runoff, and vegetated roofs can reduce runoff and evapotranspiration2.
References: = LEED v4: Building Design + Construction Guide, Achieving SSc Rainwater Management in LEED v4.1.


NEW QUESTION # 119
Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?

  • A. Plumbing fixtures
  • B. Asbestos insulation
  • C. Floor decking
  • D. Exterior glazing

Answer: C

Explanation:
Explanation
The reuse calculation for MR Credit Building Life-Cycle Impact Reduction includes the surface area of structural elements that are reused in place or salvaged and reinstalled, such as floor decking, columns, beams, and roof decking. Exterior glazing and plumbing fixtures are not considered structural elements and are not included in the reuse calculation. Asbestos insulation is a hazardous material that should be removed and disposed of properly, not reused. References: MR Credit Building Life-Cycle Impact Reduction, LEED v4 Reference Guide for Building Design and Construction123


NEW QUESTION # 120
A facility manager cleaning highly reflective paving material is

  • A. lowering the Solar Reflectance Index (SRI)
  • B. unnecessarily wasting water
  • C. increasing the heat island effect
  • D. reducing the heat island effect

Answer: D

Explanation:
Explanation
The heat island effect is the phenomenon of urban areas having higher air temperatures than surrounding rural areas due to the absorption and emission of heat by human-made surfaces, such as buildings, roads, and pavements. The heat island effect can have negative impacts on theenvironment, human health, and energy consumption. One of the strategies to reduce the heat island effect is to use highly reflective paving materials that have a high solar reflectance index (SRI), which measures the ability of a surface to reflect solar radiation and stay cool. However, over time, the paving materials can accumulate dirt and dust, which can lower their reflectance and increase their heat absorption. Therefore, a facility manager cleaning highly reflective paving material is reducing the heat island effect by restoring the reflectance and cooling potential of the surface12.
References:
*Heat Island Reduction | U.S. Green Building Council1
*SpecTopics: Heat Island Reduction Credit and LEED V4/V4.1 - Carlisle SynTec


NEW QUESTION # 121
Landscape irrigation practices consume large quantities of potable water. By evaluating the project's outdoor water budget and irrigation water demand early in the design process in Water Efficiency Prerequisite, Outdoor Water Use Reduction project teams will be able to

  • A. earn Sustainable Sites Credit, Rainwater Management
  • B. estimate and optimize water use in landscape designs
  • C. estimate and optimize water use in outdoor fountains and pools
  • D. earn Water Efficiency Credit, Water Metering

Answer: B

Explanation:
Explanation
The intent of the Water Efficiency Prerequisite, Outdoor Water Use Reduction is to reduce outdoor water consumption by either eliminating the need for irrigation or reducing the irrigation demand by at least 30% from the baseline. This prerequisite requires project teams to evaluate the project's outdoor water budget and irrigation water demand using the EPA WaterSense Water Budget Tool ora local equivalent. This will help project teams to estimate and optimize water use in landscape designs by selecting appropriate plant species and irrigation system efficiency.
References: = LEED v4: Building Design + Construction Guide, Outdoor Water Use Reduction Credits in LEED v4, Part Two: LEED v4 BD+C Outdoor Water Reduction and Related Credits


NEW QUESTION # 122
Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

  • A. A standard garbage disposal
  • B. Electronic submeter at the domestic water supply pipe to the building
  • C. An open-loop HVAC system that discharges potable cooling water to a nearby lake
  • D. Commercial dishwasher that is ENERGY STAR labeled or performance equivalent

Answer: D

Explanation:
Explanation
The Water Efficiency Credit, Indoor Water Use Reduction aims to reduce indoor water consumption by installing water-efficient fixtures and fittings, such as faucets, showerheads, toilets, and urinals1. A commercial dishwasher that is ENERGY STAR labeled or performance equivalent would help reduce the water use for dishwashing, which is one of the process water uses included in the credit calculation2. A standard garbage disposal would not reduce water use, but rather increase it. An electronic submeter at the domestic water supply pipe to the building would help measure and monitor water use, but not directly reduce it. An open-loop HVAC system that discharges potable cooling water to a nearby lake would waste a lot of water and potentially harm the environment.
References:
* Indoor Water Use Reduction
* "Maximizing Water Efficiency in Commercial Buildings: Understanding LEED BD+C Water Efficiency Credits"


NEW QUESTION # 123
......

USGBC LEED-AP-BD-C Pre-Exam Practice Tests | ExamCost: https://pass4sure.examcost.com/LEED-AP-BD-C-practice-exam.html